Master Plan Update Project Timeline

 

Project Schedule

Also see timeline for Runway Safety Area Expansion project


Begin Project: August 2009
Issues Identification: August 2009 through November 2009
Aviation Forecasts: August 2009 through December 2009
Requirements Analysis: December 2009 through March 2010
Alternatives Development and Evaluation: February 2010 through May 2010
Facility Implementation Plan: May 2010 through July 2010
Master Plan: July 2010 through December 2010
Public Involvement: August 2009 through December 2010